Project F
Time: 0 1 2 3 4
Cash flow: −$11,600 $4,150 $4,980 $2,320 $2,950

IRR

0 = −$11,600 + $4,150 + $4,980 + $2,320 + $2,950
(1+IRR)0 (1+IRR)1 (1+IRR)2 (1+IRR)3 (1+IRR)4
IRR = 10.20%

Since IRR < i, this project should be rejected.